JOHANNESBURG, GAUTENG — The escalating strain on Johannesburg sewage infrastructure due to rapid housing expansion has prompted Water and Sanitation Deputy Minister Dr Jack Bloom to advocate for decentralized wastewater solutions. Following an assessment of the failing systems in the city’s north-west, officials are urging a shift toward alternative sanitation technologies to prevent further environmental degradation and accommodate future growth.
During a site visit on Friday to the Lion Park Pump Station in the former Lion Park area of north-west Johannesburg, Bloom assessed the severe sewage challenges impacting the region. The pump station, which was funded by a property developer and commissioned in 2020, transfers sewage to the Northern Wastewater Treatment Works. However, the facility’s ongoing dysfunction has resulted in sewage pollution entering local rivers.
The area is experiencing rapid residential growth, with hundreds of townhouse units already constructed and an additional 10,000 units planned. This expansion has raised significant concerns regarding the capacity of the existing water and sanitation infrastructure. Johannesburg officials informed Bloom that further developments have been placed on hold until 2028, when additional water is expected from the Lesotho Highlands Water Project, as the city currently lacks sufficient water supply for new projects.
During the inspection, Bloom was also briefed on the nearby Zandspruit 1 and 2 sewer pump stations, which are currently non-operational. These stations feed into the Inchanga Rising Main, a critical pipeline serving Cosmo City, Zandspruit, Bloubosrand, and Northriding. Repeated bursts in the rising main have caused sewage spills in surrounding areas. Johannesburg Water assured the Deputy Minister that the most vulnerable section of the Inchanga Rising Main, along with the Zandspruit pump stations, will be repaired by February of next year. Bloom noted that these repairs are temporary measures, emphasizing that the long-term solution requires the construction of a new Lanseria Wastewater Treatment Works.
The broader issue remains that wastewater treatment capacity has failed to keep pace with housing development. To address this, Bloom referenced the Revised Compulsory National Water and Sanitation Services Standards, which were gazetted on 6 June 2025 under Section 9 of the Water Services Act of 1997. These standards strictly prohibit municipalities from approving new developments if there is insufficient wastewater treatment capacity to handle the additional sewage load.
“We cannot continue building thousands of new homes without ensuring that there is enough water to supply them and sufficient sewage capacity to dispose of the wastewater safely,” Bloom stated. He proposed that new developments utilize on-site, water-efficient sanitation systems that operate partially or completely off the municipal sewer network.
To support this transition, Bloom is advocating for tax incentives to make decentralized sanitation systems more financially viable. He also urged municipal councils to revise tariffs to reflect the reduced costs of treating sewage from developments utilizing these alternative systems, noting that technological advances are making such solutions increasingly affordable.
Beyond capacity issues, the city’s sewage network is suffering from illegal dumping. The disposal of building sand into sewer systems causes severe wear and tear on pumps. According to Bloom, Johannesburg Water spends approximately R1 million per month cleaning sand traps. He called for stricter enforcement against the illegal dumping of building materials, as well as other objects and substances such as shoes, tyres, and oil poured down manholes.
Moving forward, Bloom confirmed he will collaborate with local ward councillor Sean Kreusch to engage developers and other stakeholders. The partnership aims to implement sustainable sewage treatment solutions that support the area’s rapid housing expansion without placing further unsustainable pressure on the existing municipal infrastructure.